0%
41
1% - 29%
29
30% - 69%
4
70% - 99%
4
100% (not handed over)
3
Handed Over
0
Completed
Houses fully built (≥99%)
3 projects
5,616 units
Incomplete
Under construction
37 projects
67,980 units
Not Started
Awarded, not yet started
41 projects
35,712 units
Handed Over
Complete and handed to occupants
0 projects
0 units
Projects (81)
| Project | Region | County | Constituency | Subcounty | Units | Completion | Status | Action |
|---|---|---|---|---|---|---|---|---|
|
Kibra (Southlands) Lot 3 Project
|
Nairobi City | Nairobi | Langata | — | 2,332 |
|
Incomplete | View |
|
Jogoo Rd Phase 1 -Lot 1
|
Nairobi City | Nairobi | Makadara | — | 1,173 |
|
Incomplete | View |
|
Kamiti Social Housing Project Lot 1
|
Nairobi City | Nairobi | Roysambu | — | 2,000 |
|
Incomplete | View |
|
Kibra (Southlands) Lot 4 Project
|
Nairobi City | Nairobi | Langata | — | 1,386 |
|
Incomplete | View |
|
Maji Mazuri Modern market
|
Nairobi City | Nairobi | Kasarani | — | — |
|
Incomplete | View |
|
Jogoo Rd Phase 1 -Lot 2
|
Nairobi City | Nairobi | Makadara | — | 1,587 |
|
Incomplete | View |
|
Jogoo Rd Phase 2 -Lot 1
|
Nairobi City | Nairobi | Makadara | — | 954 |
|
Incomplete | View |
|
Mariguini Social Housing
|
Nairobi City | Nairobi | Starehe | — | 2,920 |
|
Incomplete | View |
|
Kibra (Southlands) Lot 2 Project
|
Nairobi City | Nairobi | Langata | — | 1,584 |
|
Incomplete | View |
|
Kibra (Southlands) Lot 5 Project
|
Nairobi City | Nairobi | Langata | — | 2,241 |
|
Incomplete | View |
|
Dagoretti - Ruthimitu AHP
|
Nairobi City | Nairobi | Dagoretti South | — | 2,280 |
|
Incomplete | View |
|
SEPU AHP
|
Nairobi City | Nairobi | Embakasi South | — | 4,076 |
|
Incomplete | View |
|
South B Modern market
|
Nairobi City | Nairobi | Starehe | — | — |
|
Incomplete | View |
|
Makongeni Phase 1B
|
Nairobi City | Nairobi | Makadara | — | 3,100 |
|
Incomplete | View |
|
Makongeni Phase 1A
|
Nairobi City | Nairobi | Makadara | — | 2,258 |
|
Incomplete | View |
|
Proposed Construction of the PC Kinyanjui Technical training institute Accommodation in Nairobi County (with associated social amenities and infrastructure)
|
Nairobi City | Nairobi | Dagoretti South | — | 360 |
|
Not Started | View |
|
Proposed Construction of the Kasarani technical and vocational collage Accommodation in Nairobi County (with associated social amenities and infrastructure)
|
Nairobi City | Nairobi | Kasarani | — | 570 |
|
Not Started | View |
|
Proposed Construction of the Kabete National Polytechnic Accommodation in Nairobi County (with associated social amenities and infrastructure)
|
Nairobi City | Nairobi | Westlands | — | 570 |
|
Not Started | View |
|
Proposed Construction of the Utalii College Hostels in Starehe Constituency (with associated social amenities and infrastructure)
|
Nairobi City | Nairobi | Mathare | — | 570 |
|
Not Started | View |
|
Proposed Construction of Kenya School of TVETs Hostels in Westlands Constituency
|
Nairobi City | Nairobi | Westlands | — | 570 |
|
Not Started | View |
|
ACCOMODATION- KIBRA TECHNICAL VOCATIONAL COLLEGE
|
Nairobi City | Nairobi | Kibra | — | 570 |
|
Not Started | View |
|
Proposed Construction of University of Nairobi Hostels in Starehe Constituency-
|
Nairobi City | Nairobi | Starehe | — | 3,000 |
|
Not Started | View |
|
Proposed Construction of The Cooperative University of Kenya Hostels in Langata Constituency-
|
Nairobi City | Nairobi | Langata | — | 1,200 |
|
Not Started | View |
|
Proposed Construction of Multimedia University Hostels in Langata Constituency-
|
Nairobi City | Nairobi | Langata | — | 1,200 |
|
Not Started | View |
|
Proposed Completion of 130No. Housing Units For General Service Unit (GSU) Nairobi
|
Nairobi City | Nairobi | Dagoretti North | — | 130 |
|
Not Started | View |