Back
Busia ATC Complex AHP Project- Phase 2
46.3%
Completion status
Incomplete
1,500 units · AHP
Location
Region
Western
County
Busia
Constituency
Busia Town
Subcounty
—
Project Details
Project Type
Affordable Housing Programme
Unit Type
—
Units
1,500
Acreage
—
Units in Progress
—
Tag
—
Total Cost of Ongoing Project
—
Start Date
—
End Date
—
Time Lapsed
—
Amount Certified
46.3%
People & Contacts
Region Manager
Rodgers
0724392485
Internal Region Manager
—
Lead Consultant
—
Contractor
—
Electricity Consultant
—
Source: AHP