Overview By Type By Region By County Projects
Back

Lari AHP

30%

Completion status

Incomplete

678 units · AHP

Location

Region

Metropolitan

County

Kiambu

Constituency

Lari

Subcounty

Project Details

Project Type

Affordable Housing Programme

Unit Type

Units

678

Acreage

Units in Progress

Tag

Total Cost of Ongoing Project

KES 2,008,658,066

Start Date

End Date

Time Lapsed

Amount Certified

People & Contacts

Region Manager

Don

0722374731

Internal Region Manager

Lead Consultant

Contractor

Jasir Contractors Ltd

Electricity Consultant

Remarks

Nyanduma Ward

Source: NMR Presentation.pptx