Everything below — the status cards, region chart and project table — covers the AHP portfolio only. The ministry's other housing programs (student accommodation, institutional/uniformed housing, markets, strategic partnerships) are summarized separately near the bottom of the page.
Completed
Houses fully built (≥99%)
12 projects
7,242 units
Incomplete
Under construction
168 projects
161,766 units
Available
Awarded, not yet started
51 projects
38,491 units
| Project | Location | Units | Completion | Status |
|---|---|---|---|---|
|
Starehe Point AHP
|
Starehe | 2,910 |
|
Completed |
|
Kiambu Town AHP
|
Kiambu Town | 2,080 |
|
Completed |
|
Marigat AHP
|
Baringo South | 526 |
|
Completed |
|
Mokowe AHP
|
Lamu West | 496 |
|
Completed |
|
Marsabit AHP
|
Saku | 220 |
|
Completed |
|
Elburgon AHP
|
Molo | 220 |
|
Completed |
|
Emgwen
|
Emgwen | 220 |
|
Completed |
|
Nanyuki Town AHP Phase 1
|
Laikipia East | 200 |
|
Completed |
|
Gichugu AHP
|
Gichugu | 110 |
|
Completed |
|
Kirinyaga AHP - NHC
|
Kirinyaga Central | 100 |
|
Completed |
|
Nyandarua AHP - NHC
|
Ol Kalou | 100 |
|
Completed |
|
Mabera AHP
|
Kuria West | 60 |
|
Completed |
| Category | Projects | Units | Avg. completion |
|---|---|---|---|
|
Student Accommodation
Student housing/hostel projects at TVETs, KMTCs, universities and colleges
|
206 | 131,213 |
|
|
Student Housing - Advertised
Student accommodation projects out to tender; not yet awarded
|
277 | 161,274 |
|
|
Institutional & Uniformed Services Housing
KDF, Police, Prisons, GSU, NYS and other institutional housing projects
|
379 | 170,395 |
|
|
Markets (ESP / Modern Markets)
Economic Stimulus Programme and modern market construction projects
|
316 | 0 |
|
|
Strategic Partnerships
Private developer partnership pipeline under review
|
20 | 0 |
|